Suki Kinar Hydropower Project - 884 MW

Another Milestone has been achieved at Suki Kinari Hydropower Project- 884MW

On 8th September 2021, the first Stator for Unit no.4 has been hoisted successfully and lowered into the unit pit.

The total lifting weight was 335 Tons which was accomplished with the help of the tandem operation of Bridge cranes.




1631112196260.png




1631112230013.png




1631112248420.png
 
The Suki kinari Hydropower Project is located on the Kunhar River in the beautiful valley of Kaghan, KPK Province.

1632226814279.png


As a key project in the list of the first batch of priority projects of the "China-Pakistan Economic Corridor", China Energy Construction Gezhouba Group's overseas greenfield investment "first order", the project shoulders the major mission of Gezhouba Group's transformation and upgrading and structural adjustment.

The SK Hydropower Station is equipped with four Pelton turbine generators with a single unit capacity of 221 MW, with a total installed capacity of 884 MW, a maximum net head of 922.72 m and an average annual power generation of 3.212 billion kWh for many years.

As a key project in the list of the first batch of priority projects of the "China-Pakistan Economic Corridor", China Energy Construction Gezhouba Group's overseas greenfield investment "first-order", the project shoulders the major mission of Gezhouba Group's transformation and upgrading and structural adjustment.


1632226856518.png



1632226902490.png
 
3rd breakthrough of Headrace Tunnel at Suki Kinari Hydropower Project took place on 25th September, 2021.
23.2Km long headrace tunnel is being excavated through different access Adits/Tunnels.

More than 3kilometer long tunnel sections (A1-A3) breakthrough with high-accuracy alignment.

To celebrate this important milestone, a ceremony was held at construction site and all stakeholders participated.



1632603554237.png





1632603571651.png
 
Suki Kinari Hydropower Project, a CPEC clean energy project with total capacity of 884MW, successfully achieved another remarkable milestone!


1632940561721.png




1632940539780.png
 
Another good news! | Suki Kinari Hydropower Project

The successful completion laid a solid foundation for subsequent Concrete Lining construction of the Headrace Tunnel. The total length between two sections is more than 02 kilometers. This was the 4th breakthrough of 23.2km long headrace tunnel which is being excavated from 08 access Adits and multiple working faces.
The successful completion laid a solid foundation for subsequent Concrete Lining construction of Headrace Tunnel.


1633264634859.png
 
884MW Suki Kinai Hydropower Project - CPEC Project

A Straight-of-the-art steel factory has been established within the construction site to produce Steel liner for the Headrace tunnel and Penstock system.



1634043476054.png




1634043496850.png




1634043526792.png




1634043551007.png
 
Energy China Gezhouba Group has built the most advanced Steel Processing Plant in Pakistan with an area of 4200m2 for the construction of Suki Kinari (SK) Project Hydropower, a key project listed among the first batch of priority projects in the CPEC.

The main structure of the plant is a portal frame, equipped with a 4,000t frame hydraulic press, gantry crane, CNC cutting machine, welding cross arm, and a batch of advanced equipment. The plant is designed with a peak monthly production capacity of 950 tons.

The construction and operation of the plant have effectively promoted local employment. Chinese Contractor has "tailored" training programs for Pakistani employees, managing to improve their working skills and assist them in achieving a desired professional future.
.

1635424266913.png





1635424310619.png




1635424333568.png
 
Another good news from biggest hydropower Project of CPEC..

The steel Liner for Headrace Tunnel of Suki Kinari Hydropower Project has been completed today.
23.2km long headrace tunnel passing through difficult terrain and in poor geological section, Steel lining has been designed. 5.5m diameter steel cans have been fabricated in a straight of the art steel factory at site and mobilized in HRT for installation.
A total of 117 steel cans (each 3m long) were transported and fabricated inside the tunnel.